Claim Application Letter Sample - Article 1

Dear [Insurance Company],

Subject: Claim Application for Auto Accident

I am writing this letter to officially file a claim for compensation regarding an auto accident that occurred on [Accident Date]. I was involved in a collision with another vehicle at the intersection of [Intersection Name] and [Street Name]. The accident was not my fault, and I have attached the necessary supporting documents for your reference.

At the time of the accident, I was driving my car, a [Car Make and Model], with license plate number [License Plate Number]. The other vehicle involved was a [Car Make and Model], with license plate number [License Plate Number]. The accident took place due to the negligence of the other driver, who failed to stop at a red light, resulting in a direct impact on the driver's side of my vehicle.

As a result of the accident, I sustained injuries to my neck, back, and left arm. I had to seek immediate medical attention, and I have attached medical reports from [Hospital/Clinic Name] detailing the extent of my injuries and the treatment provided. The medical expenses incurred include emergency room charges, diagnostic tests, consultations, and medication costs.

Furthermore, my vehicle suffered significant damage, including a damaged door, broken windows, and a bent frame. I have attached photographs of the accident scene and the damages sustained by my car. I have also obtained a repair estimate from [Auto Repair Shop Name], which states the estimated cost of repairs necessary to restore my vehicle to its pre-accident condition.

Considering the circumstances and the evidence provided, I kindly request that you promptly review and process my claim. I am seeking compensation for the following:

1. Medical expenses: [Total Amount]

2. Vehicle repair costs: [Total Amount]

3. Loss of income: [Amount per day multiplied by the number of days unable to work]

4. Pain and suffering: [Amount to be determined]

Please let me know if any additional information or documentation is required to support my claim. I would appreciate regular updates on the progress of my application. I trust that you will handle this matter with utmost professionalism and provide a fair resolution.

Thank you for your attention to this matter. I look forward to a prompt and favorable response.

Sincerely,

[Your Name]

[Your Contact Information]

索赔申请书范文英文 篇三

I asked a friend to buy a gift in New Zealand. The birthday gift is ready. In March, EMS (New Zealand Post's international express fee is much higher than that of ordinary people, and the odd number is ednz).

They promise that the delivery will reach the recipient within working days. As a result, they do not leave New Zealand's mail inquiry or stay in receipt The reason of the post office staff is that they suspect that there is no mobile phone separated from the battery, instead of opening it. Now the question is, why don't you inform the sender before and after the opening? As for whether the sender can open it, until today, the mail inquiry has not reached the destination.

The staff of the post office told the sender that It's been more than 4 days since I left my hair. I can't mention in my apology in March that I can't get it until next Tuesday. What's the meaning of me.

中文翻译:

我请一位朋友在新西兰买了一份礼物,生日礼物准备好了,到了xx月份一定要在新西兰xx月份提速的朋友EMS(新西兰邮政nzpost的国际快递费用比一般人要多很多,奇数都是EDNZ,他们承诺发件工作日内到达收件人手中,结果是没有留下新西兰的邮件查询,或者停留在收件状态,邮局工作人员的理由是怀疑没有手机和电池分开,而不是打开这样的事情,现在的问题是,为什么不在开通前通知发件人,也没有在开通后通知发件人至于发片人是否可以打开,直到今天,邮件查询怎么也没有到达目的地,邮局的工作人员告诉发帖人,现在离发片已经4天多了,xx月份还不能在道歉中提到下周二才能拿到,连我都有什么意思啊。

索赔申请书范文英文 篇四

^^Li Ming bought a book from the library last week. He liked it very much. He read it one minute after dinner every day.

He had a little to read and he would finish reading it. But the book was missing. He didn't lend it to others.

But he looked everywhere, but he couldn't find it. He forgot where to put the book. At last, he had to pay for the book.

He learned a lesson from it. He said to himself next time He should take good care of everything^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^.

中文翻译:

^^李明上星期从图书馆买了一本书,他非常喜欢,每天晚饭后一分钟就看了,他有一点要看,他会看完的,但书不见了他没有借给别人,但他到处找,

但找不到了,他忘了把书放在哪里了,最后他不得不为这本书付钱,他从这件事中得到了教训,他对自己说,下次他应该好好照顾一切^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^。

索赔申请书范文英文 篇五

1.

合同规定设计由雇主负责。该设计包括在一层放置变压器的一个变压器室。承包商根据2011年7月5日-10-发布的施工图纸(修订版C)建造了变压器室,这些图纸包括在附录C中。

2.

应该注意的是,虽然雇主负责支付电力局的服务和接通费,但合同规范(编号23-34-78)规定,承包商负责与电力局协调工作。协调工作包括在安装变压器之前要获得电力局对变压器室的认可。

10-

物证-5 DWP 图纸传送单 号:042,日期05/07/11

11-

物证-1 合同规范摘要 号. 23-34-78

3.

承包商于2013年1月2日致函国家电力公司,通知他们电力变压器室施工已经完工,并要求国家电力公司在2013年1月11日-12-前进行检查和批准。

4.

2013年1月8日,一名国家电力公司代表在现场会见了承包商和工程师代表,视察了变压器室,并讨论了将电力供应连接到变压器的具体事项。在视察期间,国家电力公司代表表示,变压器室似乎不符合国家电力公司的要求,但对此需要进一步核实,并将他的担忧通知了承包商。2013年1月11日的现场进度会议记要记录如下:“NEC代表于8/1/13视察了一层变压器室,并告知他担心它可能不符合NEC规范。NEC代表要研究并通知JCG。’-13-

5.

2013年1月14日,国家电力公司写信给承包商并指出:

a.

电力变压器室面积不足。

b.

进入电力变压器室的卷帘门尺寸有错误-14-。

6.

2013年1月15日,约翰逊建筑集团(JCG)致函Dawson-Wilkinson合伙企业(DWP),附有国家电力公司的意见,并以以下声明结束了这封信:“显然,这些意见可能对变压器的安装和随后的通电产生严重影响。因此,我们要求你方尽快指示我们如何处理’。-15-

7.

承包商了解到,工程师、雇主的设计师和国家电力公司举行了几次会议,会议要求要解决国家电力公司的问题。承包商进一步了解到,这一问题是由于雇主的设计师在完成设计后不久,电力局的要求发生了变化而引起的。

12-物证

10-

JCG 信函 P-1013/Let-1345/NEC,

日期

02/01/13

13-物证 11-现场进度会议纪要

号51,

日期

11/01/13

14-物证 12-NEC 信函 13/0978NC/3945

日期

14/01/13

15-

物证

13-JCG 信函 P-1013/Let-1326,

日期

15/01/13

8.

工程师于2013年2月4日发出包括电力变压器室及邻近垃圾室和维修室的修订图纸和变更工程指示-16-。修订图纸请见附录F,变更工程概述如下:

A.

拆除电力变压器室与相邻垃圾房之间现有的砌块隔墙,并进行重建,给电气变压器室增加500mm的宽度。

B.

拆除电力变压器室与相邻维修室之间现有的砌块隔墙,并进行重建,给电气变压器室增加250mm的宽度。

C.

拆除现有的铝质卷帘门和混凝土过梁,将门洞宽度增加350毫米,安装新的混凝土过梁和新的卷帘门。

D.

虽然图纸上没有详细说明,但这项工作需要处理因拆除工程而损坏的花岗岩装饰。

9.

附录D中照片是在收到指示时拍摄的,照片显示,除二次电气安装工程外,所有需要变更的三个房间都完成了装修。

索赔申请书范文英文 篇六

1.

根据国家电力公司的要求,工程师指示承包商按要求改建已经竣工的电力变压器室。

2.

该指示是在改建工程已影响到进度计划中变压器安装和调试日期、随后的通电日期以及大厦测试工作后发出的。

3.

承包商采取了各种措施,以尽量减少改建工程的工期,并用少于计划的时间完成了测试工作,从而减轻了延误。

4.

承包商通过延误分析来证明延迟事件的影响,该分析表明,这一事件对项目造成的工期延长为30天,导致竣工日期推迟到2013年3月11日。

5.

承包商已经证明,没有承包商原因的延误与这一延误事件同时发生。

6.

承包商延长竣工时间的权利包含在下列条款:

A.

第条(延误的图纸或指示)。

B.

第款(放线)。

C.

第款(竣工时间的延长)。

D.

第条(当局造成的延误)。

7.

在特定情况下,承包商认为他在一定程度上公平且合理地遵守了款(承包商的索赔)之规定,所以,如果任何未能在合同规定的时间内提交正式通知的行为被视为拒绝承包商延长工期的理由,都不能算是公平且合理的。

8.

承包商有权延长竣工时间实际上已否定了雇主获得延误赔偿金的权利。

9.

因此,承包商就本索赔提到的延迟事件要求将竣工时间延长到2013年3月11日,并要求工程师就这一事件根据合同作出公平的决定。

延期索赔检查清单

1. 导言-本节的目的和大纲。

2. 起因。

3. 影响。

4. 延误分析。

5. 通过编制进度计划说明延迟分析。

6. 修改后的竣工时间。

7. 同期延误。

8. 根据合同延长时间的权利。

9. 证明索赔人遵守了先决条件。

10. 在索赔人未遵守先绝条件的情况下提出合理的论点。

11. 免除支付雇主延误赔偿金的权利。

12. 提示工程师的义务。

13. 结论-本节的简要总结。

14. 引用的项目记录。

以上译自Andy Hewitt 的 Construction Claims & Responses